本文发表在 rolia.net 枫下论坛损失主要是电站搬迁费用,还有在远地点建电站多出的电力运输和供气费用。
总损失:6.75亿
其中,在新址建电站增加的费用:6.09亿。 我觉得这个不能算是损失。因为在新地方建电站,增加电力输送和供气费用,是增加了发电成本,但是也促进偏远地区的经济发展,还有原址土地价值增加。这些都是对安省经济有利的,有得有失,从整体上来说,起码打平。
所以实际净损失:0.66亿。
我不是会计,不知道算的对不对。请教各位大侠。以下是维基的数据:
On Oct 8, 2013 the Auditor-General reported the cost to cancel the Oakville plant at $675 million. The Auditor-General noted that had the premier's office not become involved, the OPA may have been in a position to simply wait and then exercise an option to break the contract without penalty: "We believe that the settlement with TCE will not only keep TCE whole, but may make it better than whole," Lysyk said. [14] The report estimated the Premier's Office directive to make TCE "whole" increased the payout to TCE by $225 million over what was due under the terms of the contract.
A substantial portion of the net $675 million cost of cancelling the Oakville plant and replacing it with the Napanee plant relates to the decision to locate the replacement plant farther from the location of power consumption in the GTA and farther from natural gas supplies. The Auditor General calculated increased gas supply costs and additional line transmission losses totaling of $609 million (included in the $675 million total), which are wholly or partially off-set by a savings of $275 million through a lower negotiated price for the Napanee plant更多精彩文章及讨论,请光临枫下论坛 rolia.net
总损失:6.75亿
其中,在新址建电站增加的费用:6.09亿。 我觉得这个不能算是损失。因为在新地方建电站,增加电力输送和供气费用,是增加了发电成本,但是也促进偏远地区的经济发展,还有原址土地价值增加。这些都是对安省经济有利的,有得有失,从整体上来说,起码打平。
所以实际净损失:0.66亿。
我不是会计,不知道算的对不对。请教各位大侠。以下是维基的数据:
On Oct 8, 2013 the Auditor-General reported the cost to cancel the Oakville plant at $675 million. The Auditor-General noted that had the premier's office not become involved, the OPA may have been in a position to simply wait and then exercise an option to break the contract without penalty: "We believe that the settlement with TCE will not only keep TCE whole, but may make it better than whole," Lysyk said. [14] The report estimated the Premier's Office directive to make TCE "whole" increased the payout to TCE by $225 million over what was due under the terms of the contract.
A substantial portion of the net $675 million cost of cancelling the Oakville plant and replacing it with the Napanee plant relates to the decision to locate the replacement plant farther from the location of power consumption in the GTA and farther from natural gas supplies. The Auditor General calculated increased gas supply costs and additional line transmission losses totaling of $609 million (included in the $675 million total), which are wholly or partially off-set by a savings of $275 million through a lower negotiated price for the Napanee plant更多精彩文章及讨论,请光临枫下论坛 rolia.net